Question: 1 / 400

What is the maximum duration for the Sprint Planning event in a one-month Sprint?

4 hours

8 hours

In Scrum, the duration of the Sprint Planning event is directly correlated with the length of the Sprint. For a one-month Sprint, the prescribed maximum duration for Sprint Planning is indeed 8 hours. This time frame allows the Scrum Team, which includes the Product Owner, Scrum Master, and Development Team, to discuss what can be delivered in the upcoming Sprint and how that work will be achieved.

The first part of Sprint Planning focuses on what can be delivered, where the team reviews the product backlog items and decides what will be tackled in the new Sprint. The second part delves into the details of how that work will be completed, with team members discussing their strategies and approaches.

Having a maximum of 8 hours ensures that the team has enough opportunity to engage in thorough planning, enabling better commitment and alignment on goals for the Sprint, ultimately paving the way for a successful and productive iteration. This structured approach is important in maximizing the team's effectiveness and ensuring clear communication across all roles involved.

Other options suggest durations that either under or overstate the time needed for effective planning relative to a one-month Sprint, which can impede the team's preparedness or lead to inefficient use of time.

Get further explanation with Examzify DeepDiveBeta

2 days

1 day

Next Question

Report this question